Ferry

How to choose an EHR cutover date

· About 4 min read (estimate)

To choose an EHR cutover date, work back from the date your old EHR contract ends, leave time for read-only access after go-live, and avoid billing close, payroll and weeks when key staff are away. Pick the date once the sample migration is signed off and the new system is set up, then set the freeze time, the go-live day and a fallback date.

Key points
  • Start from the old contract end date and leave room after go-live for read-only access and open claims.
  • Avoid billing close, payroll and weeks when the project owner, clinical lead or billing lead is away.
  • Lock the date only after the sample migration is signed off, and agree a fallback date at the same time.

What should you check before you pick a cutover date?

CheckWhy it mattersWho confirms
Old EHR contract end dateRead-only access and open claims need time after go-liveProject owner
Sample migration signed offThe full move should use a tested field mappingClinical and billing leads
New EHR set upUsers, templates, payers and fee schedules are ready on day oneNew EHR vendor and project owner
Billing calendarClaims and month-end close are easier to track in one systemBilling lead
Staff calendarsKey people are needed on the freeze day and the first days liveProject owner
Client scheduleA quieter day means fewer sessions to reschedule or note by handFront desk

How do you choose the date step by step?

Step 1: Work back from the contract end date

Check your current contract for the end date and any notice period, then leave time after go-live for read-only access and finishing open claims in the old system.

Step 2: Block the billing and payroll dates

Ask the billing lead which days carry month-end close, claim batches and payroll, and keep the cutover clear of them.

Step 3: Check who is away

Confirm the project owner, clinical lead and billing lead are all working on the freeze day and the first days after go-live.

Step 4: Pick the freeze time and go-live day

Choose the exact time staff stop entering data in the old system and the day they start in the new one. If your schedule allows, freeze at the end of a week and go live at the start of the next, so the full move runs while the schedule is quiet.

Step 5: Agree a fallback date

Set a second date in case the final export arrives late or the new system is not ready, so moving the cutover is a planned choice.

Step 6: Announce the date

Tell staff the freeze time and go-live day as soon as the date is locked, and give the front desk the wording for client messages. How to prepare your staff for an EHR cutover covers what each role finishes before the freeze.

When should you move the cutover date?

Moving the date early is easier than fixing records after go-live.

Frequently asked questions

What is the best day of the week for an EHR cutover?

Freezing the old system at the end of a week and going live at the start of the next often works well, because fewer sessions fall in the gap. Pick the day that fits your own schedule and billing calendar.

How far ahead should we set the cutover date?

Set it once the sample migration is signed off and the new system is set up, with enough time before the old contract ends for read-only access and open claims.

What happens between the freeze and go-live?

The final export runs, the full migration moves the data, and the first checks are done. Work that comes in during the freeze is noted and entered in the new system once it opens.

Does Ferry help set the cutover date?

Yes. Ferry agrees the timeline with you during scoping, including the freeze time and the cutover date, after reviewing a test export.

Once the date is set, work through the cutover stage of the EHR migration checklist.

How Ferry helps

Ferry migrates data between behavioral health EHRs at a fixed price, with a reconciliation report for every record type. Get a migration quote.

Talk to Ferry
Every record, safely across.
Get a migration quote

How to prepare your staff for an EHR cutover

Prepare staff for an EHR cutover: who to tell and when, what to finish before the freeze, role-based training and how to report problems after go-live.

EHR migration checklist for behavioral health practices

EHR migration checklist for behavioral health practices: six stages from inventory and field mapping through cutover, reconciliation and follow-up.

How to run a sample migration before EHR cutover

Run a sample migration before EHR cutover: pick test clients, check notes, documents, diagnoses, appointments and balances, then fix the field mapping.